2017. 01. |
|
Project Start |
2017. 08. |
|
DICE Development: Observation of the Solar Eclipse |
2017. 10. |
|
BITSE Phase A/B Start |
2018. 02. |
|
BITSE Preliminary Design Review |
2018. 08. |
|
BITSE Critical Design Review |
2019. 02. |
|
CODEX Phase A Start |
2019. 09. |
|
BITSE Launch |
2019. 10. |
|
CODEX Phase B Start |
2020. 03. |
|
CODEX System Requirements Review |
2020. 07. |
|
CODEX Preliminary Design Review |
2021. 10. |
|
CODEX Critical Design Review |
2022. 07. |
|
KASI Part FM Development Complete |
2022. 08. |
|
KASI Part Delivery |
2022. 09. |
|
Coronagraph Integration Assembly Start |
2023. 04. |
|
Coronagraph Integration Assembly Complete |
2023. 05. |
|
Coronagraph Optical Performance Test |
2023. 10. |
|
CODEX Payload Integration Assembly Complete |
2023. 11. |
|
System-Level Vibration Test |
2023. 12. |
|
Electromagnetic Compatibility Test |
2024. 02. |
|
Thermal Vacuum Test |
2024. 05. |
|
Move to KSC and ELC-sim Test |
2024. 08. |
|
Final Functional Test Before Launch |
2024. 09. |
|
Loaded onto Dragon Cargo and Awaiting Launch |
2024. 11. |
|
Launch and Installation Complete |