2017. 01.
Project Start
2017. 08.
DICE Development: Observation of the Solar Eclipse
2017. 10.
BITSE Phase A/B Start
2018. 02.
BITSE Preliminary Design Review
2018. 08.
BITSE Critical Design Review
2019. 02.
CODEX Phase A Start
2019. 09.
BITSE Launch
2019. 10.
CODEX Phase B Start
2020. 03.
CODEX System Requirements Review
2020. 07.
CODEX Preliminary Design Review
2021. 10.
CODEX Critical Design Review
2022. 07.
KASI Part FM Development Complete
2022. 08.
KASI Part Delivery
2022. 09.
Coronagraph Integration Assembly Start
2023. 04.
Coronagraph Integration Assembly Complete
2023. 05.
Coronagraph Optical Performance Test
2023. 10.
CODEX Payload Integration Assembly Complete
2023. 11.
System-Level Vibration Test
2023. 12.
Electromagnetic Compatibility Test
2024. 02.
Thermal Vacuum Test
2024. 05.
Move to KSC and ELC-sim Test
2024. 08.
Final Functional Test Before Launch
2024. 09.
Loaded onto Dragon Cargo and Awaiting Launch
2024. 11.
Launch and Installation Complete